Plant construction plan: We will rebuild our plants in three phases within five years. The construction area will increase from 16000 square meters currently to 26,000 square meters afterwards.

Phase 1: 6000sm construction area was started in Sep 2019, and main buidling structure was finished in May 2022.

Phase 2: 4000sm construction area will start to build in 2023, to enlarge production capacity of our gear box and die casting products by 20%.


Phase 3: 12000sm construction area will start to build in 2025. To enlarge our heat treatment production line and gear hobbing production line, also to increase tech staff of our current R&D center from 25 to 40.

 